The Diary of a Building – Treska T3

Strategically located in Skopje’s Centar municipality, this new luxury building promises to redefine high-quality living at what is currently the most sought-after residential location in Macedonia.

TRESKA will combine architectural excellence with unparalleled amenities, creating comfort and luxury in the very heart of Skopje.

Materials: click here
Energy class: А

For information regarding available apartments, pricing, and additional details, please contact us at 071/225-888 or 075/225-888.

25.08.2026

17.07.2026

Монтажа на прозори на 1 и 5 кат. Спроведување кабли по станови на 4 и 5 во влез 1. Бетонирање на луксери за вентилациони канали.

11.06.2026

Masonry works have been completed in both entrances. Electrical cables have been installed in Entrance 1, while works in Entrance 2 have progressed up to the 3rd floor. Vertical drainage pipes have been installed in both entrances. Drainage distribution works are ongoing on the 3rd floor in Entrance 1, while works are being carried out on the 4th floor in Entrance 2.

26.03.2026

Masonry works are currently ongoing on the 5th floor.

16.03.2026

09.03.2026

Construction of façade and partition walls is ongoing on the 4th floor. Roof construction works are in progress, including the preparation of drainage openings.

25.02.2026

Construction of façade and partition walls is ongoing on the 3rd floor, with completion of the 2nd floor works. Roof construction is in progress, and drainage opening works have commenced.

02.02.2026

Completion of façade and internal masonry works on the 1st floor is ongoing, with preparations underway for masonry works on the 2nd floor.

23.01.2026

Concrete pouring of the final roof slab has been completed. Masonry works on the 1st floor have commenced.

15.01.2026

Preparations for masonry works on the 1st floor are ongoing. Reinforcement and formwork works for the slab are in progress.

26.12.2025

Reinforcement and formwork works for columns up to the 6th floor are in progress.

13.11.2025

Reinforcement and formwork for the slab at elevation 6.46, along with installation of piping for ceiling cooling and electrical installations.

14.10.2025

Reinforcement and formwork of the slab at elevation 0.

23.09.2025

Preparation for concreting of columns.

05.09.2025

Reinforcement and preparation for concreting of wall panels.

24.07.2025

Blessing of the foundations.