The Diary of a Building - Karedo

KAREDO is a residential and commercial complex strategically located in the Skopje municipality of Karposh. This is the place where you can follow the progress of construction and the development of a modern urban center.

KAREDO stands for Office, Recreation, Home—a concept designed to create the future of a vibrant and dynamic business community. It is the perfect place for doing business and modern living, just a few steps from the Vardar River promenade and in close proximity to the city center.

The complex offers complete infrastructure, including parking facilities for cars and bicycles, making it practical, functional, and convenient.

Materials: click here

Energy class: A

For information about available apartments, prices and other details, we are waiting for you at 071/225-888 or 075/225-888.

19.05.2025

08.04.2025

16.03.2025

09.09.2025

18.06.2025

01.03.2025

01.11.2024

01.11.2024

Reinforcement and formwork are being carried out on Building K2 in preparation for slab concreting.

05.09.2024

Tiles are being installed around the elevators at the Karedo building.

05.09.2024

Reinforcement and formwork are being carried out on Building K2 in preparation for slab concreting.

21.08.2024

Active works are underway at multiple positions on the building. Currently, façade jointing is being carried out on the western side; on the 2nd floor, Hunter Douglas panels are being installed in bathrooms; and marble is being installed on the staircases down to level -1. The following works have been completed: installation of interior doors in apartments, installation of entrance doors, parquet flooring completed in apartments, and tiling completed in corridors. Skirting boards are currently being installed.

21.08.2024

21.08.2024

Concreting of the slab at elevation +3.40 is underway on Building K2.

11.07.2024

Preparation for concreting of columns and wall panels is underway on Building K2.

18.06.2024

17.06.2024

Concreting of the slab is underway on Building K2.

30.05.2024

Active works are underway at multiple positions on the building. Tile installation is in its final phase on the top floor, the cement screed has been completed, and wall and ceiling finishing (skim coating) is in progress on the 1st and 2nd floors.

30.05.2024

Concreting of the slab is underway on Building K2.

23.05.2024

22.05.2024

Active works are underway at multiple positions on the building. Gypsum wall finishes are being installed in corridors, bandaging of gypsum boards in apartments has begun, along with wall skim coating. On the 3rd floor, tiles are being installed in apartments, and cement screed works are also in progress.

25.04.2024

Active works are underway at multiple positions on the building. Façade tiling is in progress, while on the 1st floor installation of gypsum wall finishes in corridors has begun, along with preparation for cement screed installation in apartments. On the 2nd floor, tiles are being installed in kitchens and bathrooms, and heating and cooling installations are also underway in apartments.

17.04.2024

Blessing of the foundations K2.

15.04.2024

09.04.2024

Active works are underway at multiple positions on the building. Façade tiling is in progress, while on the 1st floor tile installation has begun in apartment kitchens and bathrooms. On the 2nd floor, gypsum wall finishes are being installed in apartments. Testing of the water supply installation has been completed, and installation of heating and cooling systems in apartments has also begun.

02.04.2024

20.03.2024

15.02.2024

Application of MP75 gypsum plaster on the 1st floor. Cement plastering in kitchens and bathrooms completed. Window installation completed.

02.02.2024

Installation of electrical wiring on the 3rd floor. Application of cement plaster in kitchens and bathrooms on the 2nd floor. Installation of windows on the 3rd floor.

12.11.2023

Construction of facade walls on the 1st, 2nd, and 3rd floors. Installation of water drainage systems on the 1st, 2nd, and 3rd floors. Installation of electrical wiring on the 1st and 2nd floors.

31.08.2023

26.07.2023

Masonry works are underway on facade and partition walls at the building.

28.06.2023

Works are underway at two locations on the site: roof construction is in progress on Lamella 2, while parapet construction is being carried out on Lamella 1 at platform 600.

13.06.2023

26.05.2023

09.05.2023

12.04.2023

09.03.2023

Formwork installation for the slab at elevation +9.70.

24.02.2023

Reinforcement, formwork, and preparation for concreting of the slab at elevation +6.40.

16.02.2023

Formwork and reinforcement of the slab.

09.02.2023

Concreting of columns and elevator shaft walls.

02.02.2023

Formwork, reinforcement, and preparation for concreting of the slab at elevation 3.40.

17.01.2023

29.12.2022

Preparation for reinforcement and formwork of the slab.

06.12.2022

Preparation for concreting of columns.

29.11.2022

22.11.2022

Reinforcement, formwork, and preparation for concreting of wall panels.

08.11.2022

Reinforcement of foundation footings and preparation for concreting of columns.

02.11.2022