The Diary of a Building – Treska T2

Strategically located in Skopje’s Centar municipality, this new luxury building promises to redefine high-quality living at what is currently the most sought-after residential location in Macedonia.

TRESKA will combine architectural excellence with unparalleled amenities, creating comfort and luxury in the very heart of Skopje.

Materials: click here
Energy class: А

For information regarding available apartments, pricing, and additional details, please contact us at 071/225-888 or 075/225-888.

17.07.2026

Изработка на фасада. Поставен гранит во влезови пред станови. Завршно молерисување во станови на 3 кат. Комплетирано поставување на плочки во кујни и купатила.

11.06.2026

Works are ongoing on the eastern and northern façades. Blinds have been installed in the apartments. Entrance areas with plasterboard have been completed, and tile installation is currently in progress in the kitchens and bathrooms on the penthouse floor.

26.03.2026

Ceiling heating installation has been completed, as well as the tile installation on the southern façade. Installation of the fire hydrant system is currently underway, along with tile installation on the 2nd and 3rd floors.

16.03.2026

02.02.2026

Tile installation in the kitchens and bathrooms has commenced on the 1st floor. Preparations are being made for the installation of cement screed on the 5th floor, while underfloor heating systems are being installed in the apartments on the 6th floor.

26.12.2025

27.11.2025

Underfloor heating installation has been completed up to the 5th floor. Cement screed installation is ongoing. Plasterboard finishes in the corridors have been completed. Waterproofing works in the bathrooms have been completed up to the 5th floor.

13.11.2025

Completion of underfloor heating installation up to the 3rd floor and preparation for cement screed. Installation of gypsum wall finishes in corridors on the 5th floor. Final plastering of apartments on the 5th floor. Waterproofing in bathrooms completed on the 1st floor.

14.10.2025

Installation of cement screed on the 1st floor. Underfloor heating installation in progress on the 2nd floor. Installation of gypsum wall finishes in corridors and apartments on the 4th floor. Wall finishing (skim coating) works underway in the stairwell core. We have started installing scaffolding for façade construction works.

29.04.2025

27.02.2025

15.10.2024

Construction of facade and partition walls on the 3rd floor.

04.10.2024

05.09.2024

Construction of facade and partition walls on the 1st floor.

23.08.2024

11.07.2024

Preparation for concreting of the roof slab.

30.06.2024

Preparation for concreting of columns up to the 7th floor.

30.05.2024

Preparation for concreting of columns is underway.

22.05.2024

15.05.2024