The Diary of a Building – Treska T1

Strategically located in the heart of Skopje’s Centar municipality, the Treska Complex represents a new symbol of urban and modern living at one of the most sought-after locations in Macedonia.

Built according to the proven Golden Art system, using top-quality materials from renowned manufacturers, Treska guarantees durability, safety, and prestige for its future residents.

With secured parking spaces on multiple levels, the complex will offer practicality and comfort in everyday life.

When completed, Treska will represent a new city within the capital – a vibrant, dynamic and inspiring space for future generations.

📌 Here you can follow the full progress of construction and the transformation of this unique residential and commercial complex.

Materials: click here
Energy class: А

For information regarding available apartments, pricing, and additional details, please contact us at 071/225-888 or 075/225-888.

17.07.2026

Демонтажа на фасадно скеле на влез 1. Припрема за изработка на натстрешница за рампа за во гаража.

11.06.2026

The railing in the staircase core has been installed, and the entrance area has been fully completed.

26.03.2026

The façade is in the final stage of completion. The installation of the fittings is being finalized, the staircase core has been fully painted, and the finishing works on the entrance area are also being completed.

16.03.2026

25.02.2026

The glass shopfronts for the commercial units have been installed, along with the entrance door screens. Works are currently ongoing in the staircase core, including the installation of trims and wall finishing. Fundermax façade cladding is being installed on the north and east sides.

02.02.2026

The installation of glass shopfronts for the commercial units has been completed.

23.01.2026

Parking lines have been marked on level -1. Granite has been installed on the staircases and corridors, tiles have been placed around the lifts, and the granite installation in the entrance area has been completed.

26.12.2025

27.11.2025

Granite installation is ongoing in the corridors in front of the apartments. The installation of Fundermax cladding on the eastern façade of Entrance 1 is in progress, and the installation of ventilation ducts on level -1 has been completed.

13.11.2025

Granite installation is ongoing in the corridors in front of the apartments. Waterproofing works are being carried out on the penthouse terraces. Fundermax cladding is being installed on the eastern façade of Entrance 1. Ventilation ducts are being installed on level -1.

14.10.2025

The installation of internal apartment doors has been completed. Final painting works have been completed up to the 4th floor, while glass balcony railings are being installed on the façade.

23.09.2025

Installation of internal apartment doors on the 3rd floor is ongoing. Final wall painting works are being carried out on the 2nd floor, and façade works are in progress.

11.09.2025

16.07.2025

14.06.2025

10.05.2025

07.04.2025

14.03.2025

21.02.2025

05.12.2024

15.10.2024

Installation of bathroom tiles is ongoing, along with the installation of water meters and electrical systems throughout the apartments.

06.09.2024

21.08.2024

Cement plaster application works are currently being carried out in the kitchens and bathrooms of the apartments.

11.07.2024

Multiple works are ongoing on site. On the 2nd floor, insulation structures with plasterboard are being installed, ceiling finishing works are being carried out, while electrical installations are being completed throughout the apartments on the 1st floor.

30.05.2024

Works on site are progressing actively according to the planned schedule. Cement plaster is being applied in kitchens and bathrooms on the 1st and 2nd floors, preparations are underway for window installation on the 3rd floor, and electrical cabling is also being installed throughout the apartments on the same floor.

22.05.2024

Windows are being installed on the 2nd floor, while electrical cabling works are ongoing throughout the apartments on the 1st floor.

15.05.2024

Window installation has commenced on site, along with electrical cabling works throughout the apartments on the 1st floor.

10.04.2025

29.03.2024

25.03.2024

07.03.2024

29.02.2024

Completion of masonry works on the 4th floor, preparation for masonry works on the 5th floor, and preparation for electrical installations throughout the apartments.

15.02.2024

Construction of façade and partition walls on the 4th floor. The roof structure is in the final stage of completion.

08.02.2024

29.01.2024

Construction of façade and partition walls on the 3rd and 4th floors.

22.01.2024

Roof structure works are ongoing. Construction of façade and partition walls is being carried out on the 1st and 2nd floors, while materials are being cleared from the remaining floors.

26.12.2023

Construction of the wooden roof structure. Façade wall construction is ongoing on the 1st and 2nd floors, while materials are being cleared from the remaining floors.

12.12.2023

Multiple activities are currently ongoing on site. Formwork for the roof slab is in progress, construction of façade walls on the 1st floor has commenced, and waterproofing works on the external walls are being carried out.

24.11.2023

Formwork installation for the slab.

10.11.2023

19.10.2023

Reinforcement and formwork works for the 1st-floor slab are ongoing. External wall insulation works are also being carried out.

29.09.2023

20.09.2023

Blessing of the foundations.